Esfarayen Steel Supplementary Project

The purpose of the project implementation: Increasing the production capacity of molten steel from 80 thousand tons, providing continuous casting ingots required by Radial Forging Workshop and Lule Gostar Company (producer of seamless pipes), producing high-alloy steels, diversifying the products, providing roughing equipment, tempering and peeling of forged sections, creating a heat treatment workshop for all kinds of operations including quench tempering, refining steel by ESR method, creating advanced laboratories for the production of high-alloy steels, producing heavy ingots up to 80 tons and improving the quality of products .

The subject of the project: the completion plan of casting and forging of Esfarayen Steel Complex including:

  • Completion of the existing melting section
  • Refinement of steel by melting method
  • Continuous casting line supply
  • Supplying equipment for hardening and peeling
  • Supply of machinery for heavy machinery workshop
  • Supplying equipment for the thermal process workshop
  • Supplying the laboratory department
  • Construction of buildings and relevant facilities
  • Installation and commissioning

Client: Esfarayen Industrial Complex Company

Consultant: Iran Industrial Consulting Engineers Company

Site Address: North Khorasan province – Esfarayen, km 12 of Bojnoord road.

Type of contract: EPC / Turn Key (Engineering – Supply – Construction and Installation).

Consortium:

  • Sanae Steel Industries Co. (68%)
  • INTECO (Austria) (14%)
  • DANIELI company (Italy) (18%)

Project Schedule: 36 months

 Project Status: Completed

    